To the content
225.M0009.Hochauflösende Mastfotos aus Befliegung 2017-1.jpg
Projects

Leoben Connection

The new Leoben connection will ensure supply security in the region and support increasing electrification of business and industry, for example for steel production. Thus the project will make an important contribution to the success of energy transition.

In progress

Essential for energy transitions: An additional grid supply point for the region

Demands on the power grid have increased greatly in recent decades, and demand will only continue to rise. Energy market forecasts calling for increasing electrification of the economy, industry and society clearly indicate the rising importance of having a sustainable, high-capacity electricity grid.

Electricity is becoming more and more important as a source of energy for industrial purposes above all. For example, voestalpine Stahl Donawitz GmbH plans to transition to clean steel production by 2027 by replacing the fossil fuels used in conventional steel production with renewable sources of energy. This will reduce CO2 emissions enormously and make a major contribution to the success of energy transition.

To meet future demand and maintain a high level of energy security in Austria, APG will be investing around 9 billion euros in upgrading the domestic electricity infrastructure by 2034. The new Leoben connection is part of the investment project.

Essential for energy security in the region

The existing Hessenberg substation is the main facility supplying Energienetze Steiermark?GmbH, the regional distribution system operator (DSO). APG’s planned new substation in Leoben will add another grid supply point for this DSO in the future. This will significantly improve security of supply in the region.

Crucial for the success of energy transition

The Austrian federal government has set ambitious targets for achieving energy transition. For example, the government intends for Austria to be carbon-neutral by 2040 and to cover 100% of its electricity consumption (national energy balance) from renewables by 2030.

A modern electricity infrastructure is needed to handle the growing development of renewable energy sources such as hydropower, wind energy and solar power in the region. In building the new Leoben substation with its line connection from the Hessenberg substation, APG is making an important contribution to the success of energy transition not only in this region, but in all of Austria.

Locally generated, sustainable energy can be fed into APG’s trans-regional network via the Leoben and Hessenberg substations and supplied for use Austria-wide. The same is true in reverse: sustainable electricity from other regions of Austria can be brought to the region via the two substations. The actions APG is taking will ensure that electricity from renewable sources can always be transported to wherever it is currently needed.? 

Project ticker

All current information about the project at a glance.

Project ticker

All current information about the project at a glance.

  • Update
Update 14.08.2024
Baufeld UW Leoben 2__(c)APG Ottokar Thurner..JPG

Start of construction for Leoben substation

The construction work of the Leoben substation (UW) began on July 29, 2024, as part of the "Neue Anbindung Leoben" (“New Connection Leoben”) project. The new substation will serve as additional grid support for the 110kV grid of the regional distribution grid operator and as a 220kV feed-in point for the local steel industry facilitating the construction of an electric arc furnace (EAF) at the Donawitz site. This is the basis for the production of "green steel" since it results in a considerable CO2 reduction in the steel industry. 

 

Update 11.04.2024

APG in conversation: Information day in St. Peter-Freienstein

On April 4, APG and the municipality of St. Peter-Freienstein invited landowners and residents to a project information event in the municipality's Kultursaal to discuss details of the “New Leoben Connection” project and the work around the Hessenberg substation. Just over 50 interested citizens took up the offer and spent several hours talking to APG and municipal employees. A large number of questions were answered individually and the various aspects of this project were discussed together with the interested visitors.

Translated with DeepL.com (free version)

2024 - 2026

construction phase

25

pylons

Increasing electrification

The project enables decarbonisation in the industrial sector and thus makes a significant contribution to a secure energy transition.

approx. 109 Mio €

total investment volume

2

substations Hessenberg & Leoben

6,7 km

route length

Frequently asked questions - FAQ

When will the project be implemented?

The construction phase for the Leoben connection project is scheduled to run from 2024 to 2026.

What will be done?

The route corridor for the first section of the existing 220-kV line extending from the Hessenberg substation to Ternitz will be optimised to avoid populated areas. The first line section will be built as a four-system 220-kV line until Pylon 12, where the lines will split. From here, one two-system line will continue on to Ternitz and the other will run to the Leoben substation. The Leoben substation to be newly built will serve as an additional grid supply point for Energienetze Steiermark GmbH. It will also serve as a central grid connection point for voestalpine Stahl Donawitz GmbH.

Concrete measures: 

  • Conversion & extension of the Hessenberg substation by four 220 kV switchgear panels.
  • Conversion of the existing line to a 4-system line from the Hessenberg substation to mast 12:
    • Bending between the Hessenberg substation and mast 5 as well as mast 9 and mast 12
    • Dismantling of the existing line between the Hessenberg substation and mast 5 as well as mast 9 and mast 12
  • New construction of a 2-system 220 kV line from pylon 12 to the new Leoben substation
  • New construction of the 220/110 kV substation Leoben
How many municipalities will be impacted by the project?

The project will affect two municipal areas:

  • Town of Leoben (Stadtgemeinde)
  • Market municipality of St. Peter-Freienstein (Marktgemeinde) 
How long is the route corridor and how many pylons does the project involve?

The project comprises 25 electricity pylons and the route corridor will be approximately 6.7 km long.

Does the project include substations in addition to the power line?

Yes, the project includes a total of two substations: the existing Hessenberg substation, which will undergo conversion work involving the addition of four 220-kv switchgear panels, and the 220/110-kV Leoben substation, which will be newly built as part of the project. 

The existing Hessenberg substation is the main facility supplying Energienetze Steiermark GmbH, the regional distribution system operator (DSO). APG’s planned new substation in Leoben will add another grid supply point for this DSO in the future. This will significantly improve security of supply in the region.

How does the approval process work?

A request by APG to the Styrian state government in August 2021 to determine whether the project was subject to an environmental impact assessment (EIA) revealed that the project was not subject to an EIA and thus does not require approval under the High Voltage Lines Act (Starkstromwegegesetz, StWG). At the end of June 2022, the project was submitted to the competent authorities as required by relevant Austrian state and federal law (the High Voltage Lines Act (StWG), the Nature Conservation Act, the Forestry Act, the Water Act, the Aviation Act and the Building Rights Act). 

The public  StWG negotiations took place in Leoben in September 2022. The positive StWG decisions from the Federal Ministry for Climate Action, Environment, Energy, Mobility and Technology and the Styrian provincial government have been available since December 2022.

Other specialist areas (e.g. nature conservation, forestry) were examined in individual procedures with the relevant authorities. A positive and legally binding decision has been issued for all specialist areas.

How might my property be affected?

Our power lines can impact properties in one of three ways:

  • when an electricity pylon is erected on the property;  
  • when the property is traversed by overhead transmission lines (whereby only the land within the easement area through which the lines run is impacted); and
  • when forest areas are cleared. 

The compensation to be paid for appropriated land (including agricultural land and forested areas) is stipulated in a framework agreement,  drafted in cooperation with the Styrian Chamber of Agriculture. The agreement covers the calculation of the compensation amount stipulated in the private-law easement agreements to be entered into by mutual agreement with all property owners. It also stipulates a number of general conditions relevant to the construction and operation of transmission line systems. 

The framework agreement apply equally to all land used for agricultural or forestry purposes, thus ensuring a uniform and equitable approach toward all. APG places great priority on equal treatment for all property owners. 

In the case of land that is not designated for agricultural or forestry use, separate appraisals will be made to determine the compensation amount.

The property management team is already in personal contact with the affected landowners.

Contact person

Andreas Pischel.jpg

Andreas Pischel

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 88342835 Email andreas.pischel@apg.at
Ranninger.jpg

Wolfgang Ranninger

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 415 55 68 Email wolfgang.ranninger@apg.at
Foto_Stefan Walehrach.jpg

Stefan Walehrach

Project communication

Wagramer Straße 19 (IZD-Tower)
1220 Wien

Phone +43 664 883 43 044 Email stefan.walehrach@apg.at
To the main navigation